References from over 20 years of experience in plastics processing. Hopfgartner Kunststofftechnik has references in all kinds of categories and has been one of the most significant companies in the plastics processing industry for years. The planning and development of tailor-made plastic containers, such as PE mouldings, PE containers or distribution manifolds are also part of our portfolio, as are the areas of landfill rehabilitation, plant piping or legally correct tank construction according to WHG (German Water Resource Act).


Projekt
CLIENT
SERVICE DESCRIPTION
VERSION
Heinersgrund landfill site
TS Bau GmbH NL Jena
Manufacturing and delivery of a DN 1500 PR-HD extension piece to extend an existing GRP shaft
2018
Misslbeck Kunststoffzentrum GmbH
Misslbeck Kunststoffzentrum GmbH
Manufacturing of a PE-HD washing station
2018
Eberstadt landfill site
LBU Lobenhofer Bau und Umwelt GmbH
Manufacturing and delivery of PE-EL gas collecting stations
2018
Ceramtec GmbH
CeramTec GmbH
PP-H plant piping
2018
Schwaketenbad, Konstanz
FRANK GmbH
Welding of DN 1800 and DN 1500 PE-HD pipes
2018
QSIL GmbH
QSIL GmbH
Manufacturing and delivery of a PP-H collection tray
2018
Nanoinstitut München
Manfred Himmelreich & Co. GmbH
PE plant piping
2018
LEUNA-Harze
LEUNA-Harze GmBH
Manufacturing and delivery of a DN 2400 hydrochloric acid tank made from PE-HD
2018
Aurach landfill site
AGR mbH
Repair of a gas well
2018
MEWA Manching
EnviroFALK GmbH
PP-H pipeline construction
2018
Emscherbruch central landfill site
LBU Lobenhofer Bau und Umwelt GmbH
Manufacturing and delivery of a PE-HD shaft cuff and plastic welding work
2018
Leppe central landfill site
LBU Lobenhofer Bau und Umwelt GmbH
PE heat sealing work
2018
Piesslinger GmbH, Molln
Piesslinger GmbH
Manufacturing, delivery and professional installation of PP-H cladding and PE-HD floor covering
2018
Hattingen landfill site
AGR mbH
Manufacturing and delivery of a DN 2700 shaft extension made from PE-HD
2018
Sky Plastic
Sky Plastic Recycling und Commerce GmbH
Manufacturing and delivery of a DN 2600 wastewater shaft made from PP-H, with agitator
2018
R+S Kali GmbH, Phillippsthal
F+T Müller GmbH
PE pipeline construction
2018
Guggenberg landfill site
F+T Müller GmbH
Manufacturing and delivery of penetration structures made from PE-HD
2018
Cronheim landfill site
F+T Müller GmbH
Manufacturing and delivery of penetration structures made from PE-HD
2018
Bergkamen central landfill site
LBU Lobenhofer Bau und Umwelt GmbH
Manufacturing and delivery of a DN 2000 PE intermediate shaft
2018
Langenamming landfill site
Karl-Bau GmbH
PE pipeline construction and shaft development
2018
Castrop-Rauxel central landfill site
AGR mbH
Manufacturing and delivery of PE-EL well head extensions
2018
VW AG, Wolfsburg
Fromhagen B. + L. Betriebs- und Lagereinrichtungen e.K.
Manufacturing and delivery of 26 PE-HD dosing tanks
2018
R+B Technik GmbH
R+B Technik GmbH
Manufacturing and delivery of 5 PE-HD circular tanks
2018
Max Bögl Verkehrstechnik GmbH, Tauernfeld
Naturspeicher GmbH
Plastic welding work on a heat reservoir tank
2018
Solebecken SW Friedberg
Siegfried Kiffer GmbH Anlagentechnik
Manufacturing and delivery of a refillable tank
2018
Boehringer Ingelheim
ARGE BIA LSCC Utilities
Manufacturing and delivery of 4 rectangular PP-H tanks, each with a volume of approx. 75 m³
2018
Vink Chemicals
R+B Technik GmbH
Installation of slanted floors for complete emptying of a storage tank
2018
Roter Hau landfill site
Flammer Bauunternehmung GmbH & Co. KG
PE pipeline construction
2018
Daimler AG, Sindelfingen
Bauer Resources GmbH
PP pipeline construction
2018
"Ehemaliges Rosenthal-Gelände" landfill site
TS Bau GmbH NL Jena
PE pipeline construction
2018
TWD Fibres
TWD Fibres GmbH
Manufacturing and delivery of a formic acid and hydrochloric acid tank made from PE-HD
2018
Leitz GmbH
Leitz GmbH & Co. KG
Manufacturing and delivery of a PE-HD coolant tank
2018
MVA Geiselbullach
F+T Müller GmbH
Retrofitting of a landfill seepage tank
2018
Heinersgrund landfill site
TS Bau GmbH NL Jena
Manufacturing and delivery of DN 1500 PE-EL gas water chambers
2018
Roßhaupten landfill site
Roßhauptener Kies-Gesellschaft mbH
PE pipeline construction and installation of plastic waterproofing membranes
2018
Vogelsang landfill site
LBU Lobenhofer Bau und Umwelt GmbH
Manufacturing and delivery of PE-EL gas collecting stations
2018
Burgau landfill site
Hagn Umwelttechnik GmbH
Manufacturing and delivery of DN 1000 PE ducts and pipeline construction
2017 - 2018
Audi-Campus IN
ARGE Sanierung IN-Campus GbR
Pipeline construction for groundwater remediation
2017 - 2018
ABL Technic Neuburg
ABL Technic Entlackung GmbH
Delivery and installation of PP system lines
2017
KA Tank und Rast
Schottler GmbH
Manufacturing, delivery and installation of a PE leakage control shaft
2017
Stuttgart 21
FRANK GmbH
"Welding of DN 3500 PE sewage pipes
Installation of flushing and suction lines"
2017
Castrop Rauxel central landfill site LBU
LBU Lobenhofer Bau und Umwelt GmbH
Manufacturing and delivery of PE-EL interior fittings for gas station, shaft construction
2017 - 2018
Aquachem - Schott AG
Aquachem GmbH
PP plant piping
2017
ESAU & HUEBER GmbH
Esau & Hueber GmbH
Manufacturing, delivery and professional installation of a filter tank
2017
Stockstadt landfill site
LBU Lobenhofer Bau und Umwelt GmbH
Plastic and lamination work
2017
East Karlsruhe landfill site
LBU Lobenhofer Bau und Umwelt GmbH
Rebuilding of gas collecting stations
2017
Chemiepark Gendorf
JOSEF RÄDLINGER Ingenierbau GmbH
Installation and welding of DN 1200 duct lines
2017 - 2018
Herzogenaurach landfill site
F+T Müller GmbH
Plastic shafts and dam penetration structures
2017
Emscherbruch landfill site - Holzbach shafts
AGR mbH
Retrofitting of Holzbach shafts at the central landfill site
2017 - 2018
Castrop Rauxel central landfill site
AGR mbH
Manufacturing and delivery of PE-EL gas shaft tops
2016 - 2017
MVV Gersthofen
IGS Gersthofen GmbH
Retrofitting of two wastewater pump tanks using inliner shafts, each with a volume of 50 m³
2017
Basell Polyolefine Münchsmünster
Basell Polyolefine GmbH
Repair of WHG (Water Resources Act) gutters for HDPE plant
2017 - 2018
Bauer Spezialtiefbau
Bauer Spezialtiefbau GmbH
PE volume tank with measuring cylinder
2017
BMW Dingolfingen
Bauer Resources GmbH
PE plant piping
2017
Rhön-Kaserne
Waterlau Deutschland GmbH
Delivery and on-site installation of two PP drinking-water tanks
2017
Celltechnik Lobenau
CTL Celltechnik Lobenau GmbH & Co. KG
PE cladding of an old concrete water tank, volume of 100 m³
2017
Oberhaugstett landfill site
Karl Roth GmbH & Co. KG
Pipeline and shaft construction
2017
Sansenhecken landfill site
Hermanns HTI-Bau GmbH & Co. KG/Bickhardd Bau AG
Delivery and installation of 1.5-km seepage water drainage pipes, DA 450 SDR 7.4
2017
ZF Friedrichshafen
AGO AG
PE plant piping
2017
South Munich landfill site
Gebr. Schmölzl GmbH & Co. KG
Manufacturing and delivery of PE maintenance shaft for municipal drainage system in Munich
2017
Ingolstadt Mailing wast processing plant
Zweckverband Müllverwertungsanlage Ingolstadt
Delivery and piping of various plant elements made of PP and PE
2016 - 2017
Wirmsthal, Bad Kissingen landfill site
Bauer Umwelt GmbH
Various conversions to the piping of leachate treatment plants
2016
Muttodaya Forest Monastery
Buddhistische Gesellschaft Frankenwald e. V.
Delivery and installation of a PE well schaft DN 900, lenght approx. 11 m
2016
Pfuhl, Neu-Ulm landfill site
Rti Germany GmbH
Delivery and installation of 2 leachate distribution beams and double pipelines DA 90/32
2016
Hohenpeißenberg bypass
Schneider Erd- Tiefbau GmbH
Delivery and piping of 2 lying PE leachate tanks DN 2500, length 13 m
2016 - 2017
North Munich landfill site
Hagn Umwelttechnik GmbH
PE edge shaft increase
2016 - 2017
Hohenzell, Schlüchtern landfill site
Kropp GmbH & Co. KG
Reconstruction of lanfill gas installations GUS 2 and GUS 4
2016 - 2017
Heinersgrund, Bindlach landfill site
TS Bau GmbH NL Jena
Intermediate seal - landfill gas collecting facility, delivery of gas collection well and gas shaft tops
2016 - 2018
Heinersgrund, Bindlach landfill site
TS Bau GmbH NL Jena
Rehabilitation of leachate water pipes
2016 - 2018
Georgensgmünd landfill site
Max Bögl Stiftung & Co. KG / M. Reitelshöfer GmbH
Delivery of well Chambers DN 1500 and leachate pump shaft DN 200
2016
Emscherbruch, Gelsenkrichen central landfill site
AGR mbH
Removal of the gas collecting facility - delivery of gas shaft tops
2016
Castrop-Rauxel central landfill site
bds Boden- und Deponie-Sanierungs GmbH
3. Construction section sealing - supply of gas shaft tops
2016
Blumentobel, Kirchheim unter Teck landfill site
AGR mbH
Reconstruction of landfill gas extraction - pipeline construction
2016
Außernzell landfille site
Rti Germany GmbH
Basic sealing of construction section 14 and 15 - pipeline construction
2016 - 2018
Bosch Bamberg
Albert & Bergmann GmbH & Co. KG
Delivery and istallation of 2 cooling water tanks DN 4800, net capacity 55 m³
2016
BMW AG München
EKK Anlagentechnik GmbH
PP lining of the KTL basin of the cathodic immersion paint
2015
Wirmsthal, Bad Kissingen landfill
BAUER Umwelt GmbH
Plant pipework of the new SIWA treatment plant
2015
Mihla, Buchenau landfill
SEKISUI SPR Germany GmbH
Lining of a concrete percolating water deposit with concrete protection slabs and complete welding according to BQS 8-1
2015
Emscherbruch landfill
bds GmbH
Production and supply of gas well heads and extensions according to BQS 8-1
2015
LYONDELLBASELL Münchsmünster
LYONDELLBASELL
Repair of the existing PE-EL liners in the HEXANE production plant D 741 area
2015
VW AG WOB
EKK Anlagentechnik GmbH
Supplementary work in the KTL basin hall 9
2015
Münchsmünster petrochemistry
Josef Stangelmeier Bauunternehmung GmbH & Co.KG
Shaft renovation S19, replacement of the existing defective concrete shaft and replacement with new PE shaft of class D400
2015
Heinersgrund landfill
TS Bau GmbH
Delivery and assembly of various revision shafts, edge dam penetrations and piping according to BQS 8-1
2015
Mainsite landfill
bds GmbH
Replacement of a slider DN 500 under full respiratory protection
2015
North Munich landfill
bds GmbH
Delivery and assembly of a PE rinse arch according to BQS 8-1
2015
North Munich landfill
Hagn Umwelttechnik GmbH
Extension of the existing PE edge shafts
2015
Walddorf landfill
ARGE SEKISUI SPR Germany GmbH/bds GmbH
Welding of the PE inliner in the precast concrete parts
2015
Eisenberg landfill
Kreisverwaltung Donnersbergkreis
Renovation of the PE gas well heads
2015
Traunreut municipality
Bauer Water
Piping of the groundwater treatment container plant
2015
Sulzbach, Rosenberg landfill
Bauer Umwelt GmbH
PE piping and container rebuilding
2015
NABALTEC buffer reservoir
NABALTEC AG
deliver and assemble 2 PP buffer reservoirs in segmented construction welded on-site
2015
VW AG WOB
EKK Anlagentechnik GmbH
PP lining of the KTL basin of the cathodic immersion paint hall 9
2014 - 2015
Peterswörd landfill
Bauer Umwelt GmbH
Delivery and assembly of a PE gas well shaft
2014
Gallenbach landfill
Bauer Umwelt GmbH
PE piping and container rebuilding
2014
Prototype of ECOBULL salt truck
Springer Kommunaltechnik Tirol
Planning and manufacturing of 2 prototype tanks for an EcoBull salt truck in PE blue
2014
Ingolstadt Mailing waste processing plant
Zweckverband Müllverwertungsanlage Ingolstadt
Manufacturing and assembly of a mixing vessel for optimizing wastewater treatment
2014
Frankfurt Krome
Harald Gollwitzer GmbH
Delivering and laying the PE underground pipe incl. pressure samples
2014
GSB Ebenhausen
GSB Sonderabfall- Entsorgung Ebenhausen GmbH
delivering and laying a PE double pipe duct
2014
Stockstadt landfill
KMG Pipe Technologies GmbH
Welding of the PP inliner to the precast concrete parts as well as delivery and assembly of PP ring drainages
2014
Sindelfingen landfill
bds GmbH
Manufacturing of various shafts, gas collecting stations and pipe ducts according to BQS 8-1 incl. on-site assembly
2014 - 2015
Sehlem landfill
Hermanns HTI-Bau GmbH & Co.KG
Manufacturing of various shafts, edge dam penetrations and pipe ducts according to BQS 8-1 incl. on-site assembly
2014
Riederberg landfill
Amt der Tiroler Landesregierung
Reconstruction and revision work on the degassing system
2014
Piesberg landfill
bds GmbH
Manufacturing of various parts according to BQS 8-1 and on-site assembly
2014 - 2015
Morgenstern landfill
ARGE mit bds GmbH
Renovation of a percolating water shaft with glass fiber-reinforced plastic inliners and renovation of the underground pipes
2014 - 2015
Gellenhausen-Hailer landfill
ARGE Deponie Hailer
Manufacturing of various parts according to BQS 8-1 and on-site assembly
2014
Sieghart landfill
HTI Gienger
manufacture and deliver PE gas well houses DN 1500
2014
Bornhausen landfill
bds GmbH / KMG Pipe Technologies GmbH, NL Ferrum
Welding the PE concrete shafts with PE inliner
2014
Hechingen landfill
bds GmbH
Reconstruction of the landfill degasification on the lean gas flare plant, delivery of a PE condensate separator
2014
Wilsum landfill
bds GmbH
Delivery and placement of telescopic PE gas well pipes and PE well heads
2014
Bornum landfill
bds GmbH
Reconstruction and expansion of the landfill gas collection
2014
Production of the pump shafts and special containers
PENTAIR PumpenJung GmbH
Supplier of all plastic containers above DN 1000 and special shaft construction
2014
Production of all plastic products
OEKOMAX Abscheidetechnik GmbH
Supplier of all plastic products (separators, lifting systems, pump shafts)
2014
EKK Anlagentechnik
Volume reduction and PP lining cleaning tank
2014
Waste recycling plant, Ingolstadt
Waste incinerator plant administration union
Piping of a test facility for waste water treatment
2014
Automobile industry
New ventilation ducts made of PP-s and PE-HD plastic
2013
Landfill Born Hausen, Seesen
ARGE bds / KMG
Welding of SIWA manhole shaft segments
2013 - 2014
Landfill Piesberg, Osnabrück
bds
Gas well construction
2013 - 2014
Landfill, Dachsklinge, Sindelfingen
ARGE bds / HKU
Pipe construction + shaft construction + gas station extension
2013 - 2014
New freight station Burghausen, Burghausen
Rädlinger
Welding of various ducts
2013
AUDI AG, Cathodic dip-paint 1 tank, Ingolstadt
EKK Anlagentechnik
PP liner basin 1 one of cathodic dip painting
2013
Sleeper plant of Deutsche Bahn, Schwandorf
Bauer Umwelt
Piping of a groundwater rehabilitation system
2013
BMW AG, Sedimentation tank, Munich
EKK Anlagentechnik
PP lining of sedimentation tank
2013
Alpenrind, Salzburg / Austria
Hager Tiefbau
Foil lining of cesspit
2013
Waste water treatment plant Munich II, Munich
ECOPLANT
Large pipe laying
2013
AUDI AG, Cathodic dip-paint 2 basin, Ingolstadt
EKK Anlagentechnik
PP liner tank 2 of cathodic dip painting
2013
Landfill Gallenbach, Aichach
Bauer Umwelt
Piping of a groundwater rehabilitation system
2012
Drinking water overhead tank Selzthal, Styria / Austria
Etertub
Water tank lining
2012
Drinking water overhead tank, Villnöss, South Tyrol / Italy
Etertub
Lining of seepage tank
2012
Landfill, Heinersgrund, Bayreuth
KMG
Rehabilitation of leachate inspection shaft
2012
Landfill, Stockstadt, Stockstadt
KMG
Welding of PE-coated shaft segments
2011
Landfill, Hausham, Miesbach
ARGE Hagn / KMG
Double piping construction + inspection manholes
2011 - 2012
Landfill, Freudlsperger, Neuötting
Hagn Umwelttechnik
Doppelrohrleitungsbau + Revisionsschächte
2011 - 2012
Slag heap landfill, Sulzbach-Rosenberg
Max Bögl
Shaft construction + shaft furnishings
2011 - 2013
Landfill Riederberg, Wörgl
State of Tyrol / Wehrle
Rehabilitation of leachate tank
2011
MF conduit landfill, Aurach (ARGE bds / RAM)
District Office, Ansbach
Construction of a multi-functional pipeline DN 2000 Length 130 m
2011 - 2013
Pipe rehabilitation, Aurach landfill (ARGE bds / RAM)
District Office, Ansbach
Leachate pipe rehabilitation + burstlining
2011 - 2013
North Munich landfill
Hagn Umwelttechnik
Pipe rehabilitation work + additional inspection shafts
2011 - 2014
FIBRES, Kelheim
Stanglmeier
Plant construction
2010
Landfill Außernzell
BDS
Gas stations + Shaft construction + Double pipe construction
2010 - 2014
AOK, Pasing
YIT, Deggendorf
Roof drainage
2010
MÖMAX, Eschborn
YIT, Deggendorf
Roof drainage
2010
HVB, Munich
Power plant, Munich
System construction cooling centre
2010
Basell Polyolefine, Münchsmünster
Stanglmeier
Welding of the HDPE ducts
2010
Wacker Chemie, Burghausen
Rädlinger
Pipe and sewer construction and inspection shafts
2009 - 2012
Wacker Chemie, Nünchritz
Rädlinger
Pipe and sewer construction and inspection shafts
2007 - 2012
Landfill in Aurach
HERZ
Pipe construction + shaft construction
2007 - 2012